Rock Falling Protection
Hamiltion, ON
Owner: City of Hamilton
Project cost: $1,375,000
Completion of Work: August 2021
Scope of work summary:
The project aimed to ensure the safety of motorists and pedestrians passing through the area by providing adequate rockfall protection.
The project involved the installation of heavy-duty rockfall barriers and fencing along the west side of Sherman Avenue Access. The barriers were specifically designed to mitigate the risks of rockfall from the adjacent slope, which posed a significant threat to the safety of road users.